Arizona Subdivision Stgs 1-3, 8-9 and Reservoir

Client :
  Arizona Land Limited

Engineer :
  Nigel Nalder

Contract Manager :
  Jason Routledge

Completed Value :
  $ 2,921,563

Start Date :
  Jan 2017

Practical Completion Date :
  Sep 2017

Overview :
52 + 13 lot residential subdivision located on Hart Road, Richmond. Project also included construction of a new 850,000 litre reservoir and pumping station to supply potable water to this, and future, subdivision developments in the area.

Specific Scope :
  - Sewer : 1480m of 100-225Ø uPVC and 21 manholes
  - Stormwater : 1662m of 100-900Ø pipelines and 25 x 1050-1500Ø manholes
  - Watermain : 464m of 100-150Ø uPVC and 648m of DN63 ridermains and 65 water meter / service connections
  - Pressure testing, disinfection and mains connections for new watermains
  - 1400m of service trenches for power and telecom utilities
  - Carriageway construction including 6325m² of metalcourse construction and surfacing and 1663m of concrerte kerbs and channels
  - 1385m² of concrete footpaths and 1033m² of concrete vehicle crossings
  - Construction of new 850,000 litre steel reservoir, pump station and electrical control & SCADA

Mapua Joint Jenture Subdivision

Client :
  Mapua Joint Ventures

Engineer :
  Staig and Smith

Contract Manager :
  Mark Barr / Scott Brookland

Completed Value :
  $ 3,400,000

Start Date :
  Nov 2015

Practical Completion Date :
  May 2017

Overview :
Multi stage residential subdivision development in Mapua, Tasman. Included construction of full subdivision services and roading, new sewer rising main and connection, potable water pump station and existing roading upgrade incl new roundabout.

Specific Scope :
  - Construct sewer, stormwater, watermain, power and telecom services for subdivision through multiple stages
  - 400m DN125 PE rising main and pump station
  - Pressure test and connect new sewer rising main to TDC reticulation
  - Construct new potable water pumping station and foundations for new reservoir
  - Upgrade of Seaton Valley Road for access to new residentail lots and road access to new subdivision
  - Upgrade of Mapua Drive for access to new residentail lots and road access to new subdivision
  - Construction of new roundabout at intersection of Higgs Road and Mapua Drive
  - Temporary traffic control on busy (live) roads

Carmello Grove Sundivision

Client :
  Glass House Block Ltd

Engineer :
  James Tompkinson

Contract Manager :
  Jason Routledge

Completed Value :
  $ 737,511

Start Date :
  Aug 2016

Practical Completion Date :
  Dec 2016

Overview :
16 lot residential subdivision located at 126 Wensley Road, Richmond. Ching Contracting managed full project construction from earthworks through to carriageway construction and landscaping.

Specific Scope :
  - Earthworks : 450m³ cut to fill, 1325m³ imported fill, 2000m³ strip to waste offsite
  - Sewer : 295m 100-150Ø uPVC, 4 x 10501Ø manholes
  - Stormwater : 350 100-525Ø pipelines, 6 x 1050-1350Ø manholes
  - Watermain : 180m 150Ø uPVC and 20m DM63 MDPE ridermain
  - Watermain pressure testing, disinfection and mains connections
  - 350m power service trenches and 275m of telecom trenching
  - 410m of concrete kerbs and channels
  - 1200m² metalcourse carriageway construction
  - 1000² 2 coat chipseal and 200² 50mm asphaltic concrete surfacing
  - 312m² concrete footpaths and 205m² concrete vehicle crossings

Hart Subdivision Stages A-C

Client :
  R & M Hart

Engineer :
  Roger Ashworth

Contract Manager :
  Scott Brookland

Completed Value :
  $ 829,556

Start Date :
  Nov 2015

Practical Completion Date :
  Jul 2016

Overview :
33 lot residential subdivision located at the corner of Hill Street and Harts Road, Richmond. Ching Contracting completed full construction of this project from start to finish.

Specific Scope :
  - Bulk earthworks incl. 2000m³ cut to fill and 5000m³ imported fill
  - Sewer : 800m of 100-150Ø uPVC and 20 x 1050Ø manholes
  - Stormwater : 775m of 100 to 1600Ø pipelines, 15 manholes and 11 sumps.
  - Watermain : 250m 100-150Ø uPVC and 212m DN50 MDPE ridermains.
  - 800m of service trenches
  - 570m of concrete kerbs and channels
  - 1811m² of carriageway pavement construction
  - 800m² of concrete footpaths and 450m² of concrete vehicle crossings
  - Landscaping and grassing
  - Site ESC measures, QA, testing and records for s224

3 Ridges Subdivision Stage 1

Client :
  Project Tasman Ltd

Engineer :
  Land Dimensions - Raymond Gibbins

Contract Manager :
  Scott Brookland

Completed Value :
  $ 1,622,160

Start Date :
  January 2014

Practical Completion Date :
  August 2014

Overview :
Piping of half of the creek running through the subdivision with a 1200 diameter culvert pipe. Earthworks for first stage of subdivision on a steep hilly site. Installation of services and retaining walls and the construction of roads and right of ways.

Specific Scope :
  - Removal of unsuitable material from site.
  - 25000m3 of cut to fill earthworks.
  - Install sewer, stormwater, watermains and services.
  - Installation of retaining walls and balustrade.
  - Install kerb and channel and footpaths.
  - Install new entranceway into the ridgeway.
  - Construct road and right of way.
  - Asphalt sealing.
  - Install 1200 diameter culvert pipe to pipe half of the existing creek through the fill area.
  - Very wet ground conditions on a steep working site.

Summerset Retirement Village Nelson.

Client :
  Summerset.

Engineer :
  Dave Anderson

Contract Manager :
  Scott Brookland

Completed Value :
  $5.8 million approx.

Start Date :
  2011

Practical Completion Date :
  2016

Overview :
"Construction of full civil infrastructure works from green fields through to completed village that has a mix of villa's, townhouses, cottages, care apartments, care centre and village centre. Around 350 people will call this village home.
"

Specific Scope :
  - Earthworks for completed village of approx. 10,000m3 cut to fill.
  - 20,000m3 imported fill.
  - Complete stormwater reticulation of pipes ranging from 1200mm down to 100mm.
  - Complete sewer reticulation of pipes ranging from 225mm down to 100mm.
  - Water, power, phone and irrigation reticulation of village.
  - Kerbing, footpaths, pavement construction of complete village.
  - Preparation of building pads.

Harriet Court Subdivision, Wensley Road, Richmond, Nelson.

Client :
  Wensley Road Developments Ltd.

Engineer :
  Verrall & Partners.

Contract Manager :
  Scott Brookland.

Completed Value :
  $ 749,197.51.

Start Date :
  July 2009.

Practical Completion Date :
  November 2009.

Overview :
Full construction of residential subdivision including earthworks, drainage, services, roading and landscaping.

Specific Scope :
  - Earthworks - Vegetation clearance, strip topsoil, cut to waste, cut to stockpile.
  - Drainage - Sewer, stormwater and water reticulation construction and connection to TDC reticulations.
  - Services - Trenching, bedding and bacfilling for power and telecom services.
  - Roading - Subbase, basecourse construction. 2 coat chipseal, asphalt surfacing. Roadmarking and signage.

2000 on Champion Subdivision.

Client :
  Champion Road Ltd.

Engineer :
  Land Dimensions Ltd.

Contract Manager :
  Scott Brookland.

Completed Value :
  $ 406,212.06.

Start Date :
  September 2009.

Practical Completion Date :
  December 2009.

Overview :
Full construction of residential subdivision including earthworks, drainage, services, roading and landscaping.

Specific Scope :
  - Earthworks - Vegetation clearance, strip topsoil, cut to waste, cut to stockpile.
  - Drainage - Sewer, stormwater and water reticulation construction and connection to TDC reticulations.
  - Services - Trenching, bedding and bacfilling for power and telecom services.
  - Roading - Subbase, basecourse construction. 2 coat chipseal, asphalt surfacing. Roadmarking and signage.

Appleby Hills Subdivision - Stages 3, 4 and 5.

Client :
  CBH Limited.

Engineer :
  CBH / Cameron Gibson & Wells / Land Dimensions.

Contract Manager :
  Mark Barr.

Completed Value :
  $ 1,039,474 (ongoing).

Start Date :
  April 2007 (Stage 3).

Practical Completion Date :
  Stage 5 still current at Dec 2010.

Overview :
Initially enganged as a contractor to construct drainage and services for Stage 3. Subsequently progressed onto full subdivision construction for stages 4 and 5. Design and consenting being undertaken by Land Dimensions Ltd for Stages 4 and 5. This contract is currently ongoing (stage 5) as at December 2010.

Specific Scope :
  - Installation of stormwater, sewer, water, power and telephone services.
  - Bulk earthworks.
  - Road subgrade preparation and testing.
  - Carriageway subbase and basecourse construction and testing ready for sealing.
  - Kerb & channeling and footpath construction.
  - Final surfacing.
  - Grassing.

Research Orchard Road Subdivision.

Client :
  ROR CBH Ltd.

Engineer :
  Ching Contracting Ltd.

Contract Manager :
  Mark Barr.

Completed Value :
  $ 504,322.87.

Start Date :
  January 2008.

Practical Completion Date :
  July 2008.

Overview :
Full design and build of residentail subdivision at Research Orchard Rd, Tasman. This project ultimately lead to the formation of Land Dimensions Ltd out of Ching Contracting Ltd.

Specific Scope :
  - Full design and consent for construction of the subdivision.
  - Installation of stormwater, sewer, water, power and telephone services.
  - Bulk earthworks.
  - Road subgrade preparation and testing.
  - Carriageway subbase and basecourse construction and testing ready for sealing.
  - Kerb & channeling and footpath construction.
  - Final surfacing.
  - Grassing.
  - Final sign off (224) of completed works by Tasman District Council.