3 Ridges Subdivision Stage 1

Client :
  Project Tasman Ltd

Engineer :
  Land Dimensions - Raymond Gibbins

Contract Manager :
  Scott Brookland

Completed Value :
  $ 1,622,160

Start Date :
  January 2014

Practical Completion Date :
  August 2014

Overview :
Piping of half of the creek running through the subdivision with a 1200 diameter culvert pipe. Earthworks for first stage of subdivision on a steep hilly site. Installation of services and retaining walls and the construction of roads and right of ways.

Specific Scope :
  - Removal of unsuitable material from site.
  - 25000m3 of cut to fill earthworks.
  - Install sewer, stormwater, watermains and services.
  - Installation of retaining walls and balustrade.
  - Install kerb and channel and footpaths.
  - Install new entranceway into the ridgeway.
  - Construct road and right of way.
  - Asphalt sealing.
  - Install 1200 diameter culvert pipe to pipe half of the existing creek through the fill area.
  - Very wet ground conditions on a steep working site.

Summerset Retirement Village Nelson.

Client :
  Summerset.

Engineer :
  Dave Anderson

Contract Manager :
  Scott Brookland

Completed Value :
  $5.8 million approx.

Start Date :
  2011

Practical Completion Date :
  2016

Overview :
"Construction of full civil infrastructure works from green fields through to completed village that has a mix of villa's, townhouses, cottages, care apartments, care centre and village centre. Around 350 people will call this village home.
"

Specific Scope :
  - Earthworks for completed village of approx. 10,000m3 cut to fill.
  - 20,000m3 imported fill.
  - Complete stormwater reticulation of pipes ranging from 1200mm down to 100mm.
  - Complete sewer reticulation of pipes ranging from 225mm down to 100mm.
  - Water, power, phone and irrigation reticulation of village.
  - Kerbing, footpaths, pavement construction of complete village.
  - Preparation of building pads.

Harriet Court Subdivision, Wensley Road, Richmond, Nelson.

Client :
  Wensley Road Developments Ltd.

Engineer :
  Verrall & Partners.

Contract Manager :
  Scott Brookland.

Completed Value :
  $ 749,197.51.

Start Date :
  July 2009.

Practical Completion Date :
  November 2009.

Overview :
Full construction of residential subdivision including earthworks, drainage, services, roading and landscaping.

Specific Scope :
  - Earthworks - Vegetation clearance, strip topsoil, cut to waste, cut to stockpile.
  - Drainage - Sewer, stormwater and water reticulation construction and connection to TDC reticulations.
  - Services - Trenching, bedding and bacfilling for power and telecom services.
  - Roading - Subbase, basecourse construction. 2 coat chipseal, asphalt surfacing. Roadmarking and signage.

2000 on Champion Subdivision.

Client :
  Champion Road Ltd.

Engineer :
  Land Dimensions Ltd.

Contract Manager :
  Scott Brookland.

Completed Value :
  $ 406,212.06.

Start Date :
  September 2009.

Practical Completion Date :
  December 2009.

Overview :
Full construction of residential subdivision including earthworks, drainage, services, roading and landscaping.

Specific Scope :
  - Earthworks - Vegetation clearance, strip topsoil, cut to waste, cut to stockpile.
  - Drainage - Sewer, stormwater and water reticulation construction and connection to TDC reticulations.
  - Services - Trenching, bedding and bacfilling for power and telecom services.
  - Roading - Subbase, basecourse construction. 2 coat chipseal, asphalt surfacing. Roadmarking and signage.

Appleby Hills Subdivision - Stages 3, 4 and 5.

Client :
  CBH Limited.

Engineer :
  CBH / Cameron Gibson & Wells / Land Dimensions.

Contract Manager :
  Mark Barr.

Completed Value :
  $ 1,039,474 (ongoing).

Start Date :
  April 2007 (Stage 3).

Practical Completion Date :
  Stage 5 still current at Dec 2010.

Overview :
Initially enganged as a contractor to construct drainage and services for Stage 3. Subsequently progressed onto full subdivision construction for stages 4 and 5. Design and consenting being undertaken by Land Dimensions Ltd for Stages 4 and 5. This contract is currently ongoing (stage 5) as at December 2010.

Specific Scope :
  - Installation of stormwater, sewer, water, power and telephone services.
  - Bulk earthworks.
  - Road subgrade preparation and testing.
  - Carriageway subbase and basecourse construction and testing ready for sealing.
  - Kerb & channeling and footpath construction.
  - Final surfacing.
  - Grassing.

Research Orchard Road Subdivision.

Client :
  ROR CBH Ltd.

Engineer :
  Ching Contracting Ltd.

Contract Manager :
  Mark Barr.

Completed Value :
  $ 504,322.87.

Start Date :
  January 2008.

Practical Completion Date :
  July 2008.

Overview :
Full design and build of residentail subdivision at Research Orchard Rd, Tasman. This project ultimately lead to the formation of Land Dimensions Ltd out of Ching Contracting Ltd.

Specific Scope :
  - Full design and consent for construction of the subdivision.
  - Installation of stormwater, sewer, water, power and telephone services.
  - Bulk earthworks.
  - Road subgrade preparation and testing.
  - Carriageway subbase and basecourse construction and testing ready for sealing.
  - Kerb & channeling and footpath construction.
  - Final surfacing.
  - Grassing.
  - Final sign off (224) of completed works by Tasman District Council.